Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Saharanpur | NKG-PRIMUS (JV) | 20069031 | Nadrana & Ishaqpur MV WSS | 325.00 | 85.68 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 0 | 0 | NA | 25 | NA | No | 12361.00 | 12000.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Saharanpur | Sadhauli Kadeem | Ishaqpur | 383428 | Ishaqpur Chenchi | 271 | 260 | 96 | Work In Progress | Not Certified |
| 2 | Saharanpur | Sadhauli Kadeem | Naadrana | 383429 | Nadrana | 194 | 185 | 95 | Work In Progress | Not Certified |
| 3 | Saharanpur | Sadhauli Kadeem | Naadrana | 383430 | MAL MAZRA | 66 | 66 | 100 | Har Gar Jal | Not Certified |