Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Meerut
AGENCY Power Mech Projects Ltd
SCHEME ID 20069062
SCHEME NAME MAKHANNAGAR & TAJPURA
ESTIMATED COST 437.85
EXPENDITURE 235.74
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 0
Work Completed 1
Solar Plant
Required 37
Procured 37 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 13896.00 Meter
Length Laid 12950.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Meerut Hastinapur Tajpura 391485 Tajpura 255 246 96% Work In Progress Not Certified
2 Meerut Hastinapur Makhannagar 391501 Makhannagar 524 523 100% Work In Progress Not Certified