Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | AFCONS | 20069124 | JUNEDPUR & PURA ASHALAT KHAN VILLAGE WATER SUPPLY SCHEME | 448.34 | 139.33 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 27 | 27 | Yes | 0 | NA | No | 19607.00 | 17565.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Suithkala | Junedpur | 468167 | Junedpur | 168 | 159 | 95 | Work In Progress | Not Certified |
| 2 | Jaunpur | Suithkala | Junedpur | 468168 | Poorabechu | 43 | 41 | 95 | Work In Progress | Not Certified |
| 3 | Jaunpur | Suithkala | Junedpur | 468169 | Ashokpur Khurd | 139 | 132 | 95 | Work In Progress | Not Certified |
| 4 | Jaunpur | Suithkala | Pura Ashalat Khan | 468177 | Pura Ashalat Khan | 292 | 218 | 75 | Work In Progress | Not Certified |