Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Balrampur | Larsen & Toubro Ltd | 20069207 | SEMRAHWA WATER SUPPLY | 330.34 | 128.06 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 18 | 18 | Yes | 0 | NA | No | 13532.00 | 11830.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Balrampur | Pachperwa | Semrahwa | 444042 | Semrahn | 121 | 110 | 91 | Work In Progress | Not Certified |
| 2 | Balrampur | Pachperwa | Semrahwa | 444043 | Madni | 158 | 110 | 70 | Work In Progress | Not Certified |
| 3 | Balrampur | Pachperwa | Semrahwa | 444044 | Sadni | 36 | 24 | 67 | Work In Progress | Not Certified |