Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Balrampur | Larsen & Toubro Ltd | 20069280 | Banse Dila Water Supply | 191.01 | 119.38 | view more |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 11 | 11 | Yes | 0 | NA | No | 5499.00 | 5055.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Balrampur | Balrampur | Banse Dila | 443710 | Tenduwa | 77 | 77 | 100 | Har Gar Jal | Certified |
| 2 | Balrampur | Balrampur | Banse Dila | 443711 | Banse Dila | 140 | 140 | 100 | Har Gar Jal | Certified |