Scheme Details
DISTRICT Sultanpur
AGENCY Vindhya-GAJA (JV)
SCHEME ID 20069322
SCHEME NAME MAHMADPUR & UNDORKHA WATER SUPPLY SCHEME
ESTIMATED COST 433.94
EXPENDITURE 231.72
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 23
Procured 23 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 37704.00 Meter
Length Laid 28595.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Sultanpur Akhand Nagar Undorkha 441475 Undorkha 359 352 98% Work In Progress Not Certified
2 Sultanpur Akhand Nagar Undorkha 441476 Khakhra 37 34 92% Work In Progress Not Certified
3 Sultanpur Akhand Nagar Mahmadpur 441478 Mahmadpur 245 238 97% Work In Progress Not Certified