Scheme Details
DISTRICT
Pratapgarh
AGENCY
JMC - Lakshmi (JV)
SCHEME ID
20069510
SCHEME NAME
NEWADA KHURD WATER SUPPLY SCHEME
ESTIMATED COST
272.76
EXPENDITURE
143.13
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
4
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
18
Procured
18
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
17326.00
Meter
Length Laid
16578.00
Meter
Scheme Assigned Villages
4 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Pratapgarh | Babaganj | Newada Khurd | 429024 | Newada Khurd | 144 | 142 | 99% | Work In Progress | Not Certified |
| 2 | Pratapgarh | Babaganj | Newada Khurd | 429025 | Sanda Harakhpur | 158 | 158 | 100% | Har Ghar Jal | Not Certified |
| 3 | Pratapgarh | Babaganj | Newada Khurd | 429026 | Kotilabadi | 29 | 29 | 100% | Har Ghar Jal | Not Certified |
| 4 | Pratapgarh | Babaganj | Newada Khurd | 429027 | Nirmal Khurd | 102 | 102 | 100% | Har Ghar Jal | Not Certified |