Scheme Details
DISTRICT
Budaun
AGENCY
PNC-SPML-JV
SCHEME ID
20069574
SCHEME NAME
jasupur & alinagar water supply scheme
ESTIMATED COST
343.07
EXPENDITURE
89.17
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
23
Procured
23
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
13508.00
Meter
Length Laid
13508.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Budaun | Islamnagar | Jasupur | 401227 | Jagdishpur | 87 | 87 | 100% | Har Ghar Jal | Certified |
| 2 | Budaun | Islamnagar | Jasupur | 401228 | Jasupur | 142 | 142 | 100% | Har Ghar Jal | Certified |
| 3 | Budaun | Islamnagar | Alinagar | 401234 | Alinagar | 255 | 251 | 98% | Work In Progress | Not Certified |