Scheme Details

S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Automation Integration Status
1 Budaun PNC-SPML-JV 20069584 allipur tappa haweli & Daulatpur water supply scheme 283.51 90.33 Not Integrated

Scheme Physical Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
2 1 1 1 1 1 1 0 20 20 Yes 0 NA No 8729.00 8000.00

Scheme Assigned Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified
1 Budaun Sahaswan Allipur Tappa Haveli 401492 Allipur Tappa Haveli 173 165 95 Work In Progress Not Certified
2 Budaun Sahaswan Daulatpur 401598 Daulatpur 148 147 99 Work In Progress Not Certified