Scheme Details
DISTRICT
Pratapgarh
AGENCY
JMC - Lakshmi (JV)
SCHEME ID
20069619
SCHEME NAME
Sarai Murar Singh Water Supply Scheme
ESTIMATED COST
250.23
EXPENDITURE
136.49
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
20
Procured
20
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
12376.00
Meter
Length Laid
12276.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Pratapgarh | Mandhyatha | Sarai Murar Singh | 430015 | Sarai Murar Singh | 257 | 243 | 95% | Work In Progress | Not Certified |
| 2 | Pratapgarh | Mandhyatha | Sarai Murar Singh | 430016 | Dhaurahra | 67 | 67 | 100% | Har Ghar Jal | Not Certified |