Scheme Details
DISTRICT
Saharanpur
AGENCY
NKG-PRIMUS (JV)
SCHEME ID
20069691
SCHEME NAME
AGWAN HERA GP WSS
ESTIMATED COST
253.24
EXPENDITURE
135.84
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
23
Procured
23
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
9159.00
Meter
Length Laid
8700.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Saharanpur | Sarsawa | Agwan Heda | 384043 | Agwan Hera | 740 | 740 | 100% | Har Ghar Jal | Not Certified |