Scheme Details
DISTRICT
Saharanpur
AGENCY
NKG-PRIMUS (JV)
SCHEME ID
20069849
SCHEME NAME
TIDAULUI GP WSS
ESTIMATED COST
285.80
EXPENDITURE
127.49
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
27
Procured
27
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
11319.00
Meter
Length Laid
12500.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Saharanpur | Gangoh | Tidaului | 384191 | Tidaului | 573 | 563 | 98% | Work In Progress | Not Certified |