Scheme Details
DISTRICT
Pratapgarh
AGENCY
JMC - Lakshmi (JV)
SCHEME ID
20070073
SCHEME NAME
Udapur & Saraidasu Water Supply Scheme
ESTIMATED COST
274.61
EXPENDITURE
98.32
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
5
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
20
Procured
20
KW
Work Status
No
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
20871.00
Meter
Length Laid
20771.00
Meter
Scheme Assigned Villages
5 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Pratapgarh | Lakshmanpur | Udapur | 429148 | Udapur | 172 | 131 | 76% | Work In Progress | Not Certified |
| 2 | Pratapgarh | Lakshmanpur | Sarai Dasu | 429149 | Gosainpur | 47 | 47 | 100% | Har Ghar Jal | Not Certified |
| 3 | Pratapgarh | Lakshmanpur | Sarai Dasu | 429150 | Tarapur | 45 | 44 | 98% | Work In Progress | Not Certified |
| 4 | Pratapgarh | Lakshmanpur | Sarai Dasu | 429151 | Sarai Dasu | 72 | 72 | 100% | Har Ghar Jal | Not Certified |
| 5 | Pratapgarh | Lakshmanpur | Sarai Dasu | 429152 | Hindupur | 22 | 22 | 100% | Har Ghar Jal | Not Certified |