Scheme Details
DISTRICT Raebareli
AGENCY Vindhya-GAJA (JV)
SCHEME ID 20070093
SCHEME NAME SHAHJADPUR WATER SUPPLY Merge SCHEME
ESTIMATED COST 321.78
EXPENDITURE 207.36
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 23
Procured 23 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 14123.00 Meter
Length Laid 14000.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Raebareli Sataon Shahjadpur 416805 Shahjadpur 209 174 83% Work In Progress Not Certified
2 Raebareli Sataon Bans 416807 Bans 247 214 87% Work In Progress Not Certified