Scheme Details
DISTRICT
Mainpuri
AGENCY
NCC Ltd.
SCHEME ID
20070101
SCHEME NAME
JAGANATHPUR + KAILASHPUR + MUHABBATPUR LABHUYA GRAM PANCHAYAT WATER SUPPLY SCHEME
ESTIMATED COST
518.23
EXPENDITURE
276.56
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
2
Boring Done
2
Air Compressor Done
2
O.P. Unit Done
2
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
10
Procured
10
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
29427.00
Meter
Length Laid
28710.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Mainpuri | Barnahal | Jaganathpur | 400279 | Jagannathpur | 206 | 199 | 97% | Work In Progress | Not Certified |
| 2 | Mainpuri | Barnahal | Kailashpur | 400290 | Kailashpur | 179 | 174 | 97% | Work In Progress | Not Certified |
| 3 | Mainpuri | Barnahal | Muhabbatpur Labhuya | 400292 | Muhabbatpur Labhuya | 264 | 262 | 99% | Work In Progress | Not Certified |