Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Pratapgarh
AGENCY JMC - Lakshmi (JV)
SCHEME ID 20070110
SCHEME NAME PURE SUKHDEV & BAGIYAPUR
ESTIMATED COST 540.88
EXPENDITURE 259.37
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 2
Boring Done 2
Air Compressor Done 2
O.P. Unit Done 2
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 39
Procured 39 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 27242.00 Meter
Length Laid 27142.00 Meter

Scheme Assigned Villages

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Pratapgarh Mandhyatha Pure Sukhdev 429951 Pure Sukhdev 435 402 92% Work In Progress Not Certified
2 Pratapgarh Mandhyatha Pure Sukhdev 429952 Sadullapur 93 84 90% Work In Progress Not Certified
3 Pratapgarh Mandhyatha Bagiyapur 429953 Bagiyapur 274 274 100% Har Ghar Jal Not Certified