Scheme Details
DISTRICT
Moradabad
AGENCY
NKG-PRIMUS (JV)
SCHEME ID
20070290
SCHEME NAME
Hansoopura Village Water Supply Scheme
ESTIMATED COST
200.23
EXPENDITURE
73.24
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
25
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
8574.00
Meter
Length Laid
8000.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Moradabad | Dilari | HANSOOPURA | 387916 | FATANPUR | 142 | 140 | 99% | Work In Progress | Not Certified |
| 2 | Moradabad | Dilari | HANSOOPURA | 387918 | HANSOOPURA | 180 | 165 | 92% | Work In Progress | Not Certified |