Scheme Details
DISTRICT Moradabad
AGENCY NKG-PRIMUS (JV)
SCHEME ID 20070292
SCHEME NAME Lalpur Titri Village Water Supply Scheme.
ESTIMATED COST 176.42
EXPENDITURE 80.20
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 0
Procured 0 KW
Work Status NA
Electric
Required 25
Transformer Procured NA
Work Status No
Distribution Line
Total Length 5485.00 Meter
Length Laid 5380.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Moradabad Mundapandey Lalpur Titri 388355 Kohanku 146 140 96% Work In Progress Not Certified
2 Moradabad Mundapandey Lalpur Titri 388356 Lalpur Titri 151 142 94% Work In Progress Not Certified