Scheme Details
DISTRICT
Raebareli
AGENCY
Vindhya-GAJA (JV)
SCHEME ID
20070301
SCHEME NAME
BHAGIPUR WATER SUPPLY Merge SCHEHE
ESTIMATED COST
300.21
EXPENDITURE
214.41
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
20
Procured
20
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
14122.00
Meter
Length Laid
14000.00
Meter
Scheme Assigned Villages
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Raebareli | Unchahar | Bhagipur | 417584 | Bhagipur | 94 | 94 | 100% | Har Ghar Jal | Certified |
| 2 | Raebareli | Unchahar | Bhagipur | 417585 | Gopapur | 132 | 127 | 96% | Work In Progress | Not Certified |
| 3 | Raebareli | Unchahar | Manipur Bhatehari | 417586 | Manipur Bhatehari | 204 | 204 | 100% | Har Ghar Jal | Certified |