Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Raebareli | Vindhya-GAJA (JV) | 20070427 | ATARA WATER SUPPLY Merge Scheme | 540.08 | 251.17 | view more |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 30 | 30 | Yes | 0 | NA | No | 27610.00 | 27552.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Raebareli | Maharajganj | Atara | 416351 | Atara | 244 | 228 | 93 | Work In Progress | Not Certified |
| 2 | Raebareli | Maharajganj | Bara Huwan | 416355 | Bara Huwan | 305 | 253 | 83 | Work In Progress | Not Certified |
| 3 | Raebareli | Maharajganj | Indaura | 416356 | Indaura | 147 | 137 | 93 | Work In Progress | Not Certified |
| 4 | Raebareli | Maharajganj | Indaura | 416357 | Benipur | 19 | 19 | 100 | Har Gar Jal | Not Certified |