Scheme Details
DISTRICT
Sultanpur
AGENCY
Vindhya-GAJA (JV)
SCHEME ID
20070660
SCHEME NAME
BAHADURPUR & TAJKHANPUR WATER SUPPLY SCHEME
ESTIMATED COST
387.08
EXPENDITURE
151.09
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
0
O.P. Unit Done
0
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
30
Procured
30
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
13124.00
Meter
Length Laid
405.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sultanpur | Dubepur | Bahadurpur | 440391 | Bahadurpur | 369 | 142 | 38% | Work In Progress | Not Certified |
| 2 | Sultanpur | Dubepur | Tajkhanpur | 440392 | Tajkhanpur | 199 | 54 | 27% | Work In Progress | Not Certified |