Scheme Details
DISTRICT
Sambhal
AGENCY
SPML Infra
SCHEME ID
20070661
SCHEME NAME
Nahar Thair W/S Scheme
ESTIMATED COST
337.61
EXPENDITURE
197.10
AUTOMATION STATUS
Disconnected
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
27
Procured
27
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
13626.00
Meter
Length Laid
13626.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sambhal | Sambhal | Nahar Thair | 389124 | Nahar Thair | 516 | 516 | 100% | Har Ghar Jal | Certified |
| 2 | Sambhal | Sambhal | Nahar Thair | 389125 | Bholeshwar | 139 | 139 | 100% | Har Ghar Jal | Certified |
| 3 | Sambhal | Sambhal | Nahar Thair | 389127 | SHEHWAZPUR KHURD | 42 | 42 | 100% | Har Ghar Jal | Certified |