Scheme Details
DISTRICT
Moradabad
AGENCY
NKG-PRIMUS (JV)
SCHEME ID
20070744
SCHEME NAME
Abhanpur Kundarki and Seelpur Village Water Supply Scheme
ESTIMATED COST
399.69
EXPENDITURE
143.03
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
37
Procured
37
KW
Work Status
NA
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
15077.00
Meter
Length Laid
14400.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Moradabad | Dingarpur | Seelpur | 388449 | Seelpur | 554 | 553 | 100% | Work In Progress | Not Certified |
| 2 | Moradabad | Dingarpur | Abhanpur Kundarki | 388453 | Abhanpur Kundarki | 214 | 213 | 100% | Work In Progress | Not Certified |