Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Scheme Details

S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Automation Integration Status
1 Shahjahanpur NCC Ltd. 20070912 BHAVANIPUR & DEENG WSS 258.25 118.47 Not Integrated

Scheme Physical Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
3 1 1 1 1 1 1 0 15 15 Yes 0 NA No 7668.00 7400.00

Scheme Assigned Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified
1 Shahjahanpur Nigohi DEENG 406872 MAHOLIYA 134 130 97 Work In Progress Not Certified
2 Shahjahanpur Nigohi Bhawanipur 406873 Bhavanipur 205 205 100 Har Gar Jal Not Certified
3 Shahjahanpur Nigohi DEENG 406874 Deeng 138 132 96 Work In Progress Not Certified