Scheme Details
DISTRICT
Jaunpur
AGENCY
AFCONS
SCHEME ID
20071070
SCHEME NAME
MOOLNAPUR VILLAGE WATER SUPPLY SCHEME
ESTIMATED COST
290.69
EXPENDITURE
123.96
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
16
Procured
0
KW
Work Status
NA
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
12814.00
Meter
Length Laid
9847.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Khuthan | Moolnapur | 468660 | Molnapur | 147 | 140 | 95% | Work In Progress | Not Certified |
| 2 | Jaunpur | Khuthan | Moolnapur | 468661 | Zameen Basti | 70 | 67 | 96% | Work In Progress | Not Certified |
| 3 | Jaunpur | Khuthan | Moolnapur | 468662 | Basti Bandgan | 113 | 109 | 96% | Work In Progress | Not Certified |