Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Amethi | Vindhya-GAJA (JV) | 20071127 | SARWANPUR & KEHRAUNA & KATRAPHOOL KUNWAR WATER SUPPLY SCHEME | 953.79 | 726.72 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 7 | 2 | 2 | 2 | 2 | 1 | 1 | 0 | 60 | 60 | Yes | 0 | NA | No | 47203.00 | 44218.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Amethi | Amethi | Kehrauna | 439747 | Kehrauna | 301 | 299 | 99 | Work In Progress | Not Certified | 
| 2 | Amethi | Amethi | Sarvanpur | 439748 | Sarwan Pur | 377 | 362 | 96 | Work In Progress | Not Certified | 
| 3 | Amethi | Amethi | Kehrauna | 439749 | Sarai Raj Shah | 52 | 52 | 100 | Har Gar Jal | Not Certified | 
| 4 | Amethi | Amethi | Katra Phool Kunwar | 439750 | Katra Phool Kunwar | 265 | 265 | 100 | Har Gar Jal | Not Certified | 
| 5 | Amethi | Amethi | Katra Phool Kunwar | 439751 | Baghawaria | 63 | 63 | 100 | Har Gar Jal | Not Certified | 
| 6 | Amethi | Amethi | Katra Phool Kunwar | 439752 | Parsauli | 187 | 187 | 100 | Har Gar Jal | Not Certified | 
| 7 | Amethi | Amethi | Katra Phool Kunwar | 439753 | Jaggi Patti | 59 | 59 | 100 | Har Gar Jal | Not Certified |