Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Amroha
AGENCY SPML Infra
SCHEME ID 20071291
SCHEME NAME SALEMPUR GOSAIN SVS (S)
ESTIMATED COST 266.19
EXPENDITURE 26.92
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 1
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 39
Procured 39 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 10938.00 Meter
Length Laid 10938.00 Meter

Scheme Assigned Villages

1 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Amroha Gajraula Salempur Gosai 390946 Salempur Gosai 1061 1059 100% Work In Progress Not Certified