Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Shahjahanpur | NCC Ltd. | 20071554 | SADIK JAITPUR & SARAI TA. BANGAON WSS | 328.90 | 152.09 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 18 | 18 | Yes | 0 | NA | No | 15749.00 | 15700.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Shahjahanpur | Mirzapur | Sadikpur Jaitpur | 407584 | Sadikpur Jaitpur | 212 | 212 | 100 | Har Gar Jal | Certified |
| 2 | Shahjahanpur | Mirzapur | Sadikpur Jaitpur | 407585 | Pihani | 39 | 39 | 100 | Har Gar Jal | Certified |
| 3 | Shahjahanpur | Mirzapur | Sarai Ta. Bangaon | 407591 | Sarai Ta. Bangaon | 383 | 383 | 100 | Har Gar Jal | Not Certified |