Scheme Details
DISTRICT
Kasganj
AGENCY
PNC-SPML-JV
SCHEME ID
20071586
SCHEME NAME
BARHARI BAISYA
ESTIMATED COST
196.67
EXPENDITURE
72.60
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
20
Procured
20
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
6106.00
Meter
Length Laid
6106.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Kasganj | Kasganj | BADHARI VAISHYA | 398677 | BADHARI VAISHYA | 386 | 386 | 100% | Har Ghar Jal | Not Certified |