Scheme Details
DISTRICT
Muzaffarnagar
AGENCY
NKG-PRIMUS (JV)
SCHEME ID
20071727
SCHEME NAME
NAROTTAMPUR &BARWALA MV WSS
ESTIMATED COST
786.92
EXPENDITURE
338.68
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
2
Boring Done
2
Air Compressor Done
2
O.P. Unit Done
2
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
87
Procured
87
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
23705.00
Meter
Length Laid
23700.00
Meter
Scheme Assigned Villages
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Muzaffarnagar | Baghra | Narottampur | 385168 | Narottampur | 332 | 308 | 93% | Work In Progress | Not Certified |
| 2 | Muzaffarnagar | Baghra | Barwala | 385169 | Barwala | 1655 | 1001 | 60% | Work In Progress | Not Certified |