Scheme Details
DISTRICT
Saharanpur
AGENCY
NKG-PRIMUS (JV)
SCHEME ID
20072486
SCHEME NAME
ALLIPUR SAMBHALKI AHT. MV WSS
ESTIMATED COST
312.05
EXPENDITURE
88.95
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
5
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
25
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
10853.00
Meter
Length Laid
10500.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
5 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Saharanpur | Muzaffarabad | Alipur Sanbhaliki Aht. | 383626 | Allipur Sanbhaliki Aht. | 154 | 151 | 98% | Work In Progress | Not Certified |
| 2 | Saharanpur | Muzaffarabad | Alipur Sanbhaliki Aht. | 383627 | Ibrahimpur Must. | 84 | 72 | 86% | Work In Progress | Not Certified |
| 3 | Saharanpur | Muzaffarabad | Alipur Sanbhaliki Aht. | 677683 | Alipur Sanbhaliki Mustkam | 153 | 145 | 95% | Work In Progress | Not Certified |
| 4 | Saharanpur | Muzaffarabad | Alipur Sanbhaliki Aht. | 677684 | Gangoli | 146 | 145 | 99% | Work In Progress | Not Certified |
| 5 | Saharanpur | Muzaffarabad | Alipur Sanbhaliki Aht. | 678359 | Ibrahimpur Aht. | 7 | 1 | 14% | Work In Progress | Not Certified |