Scheme Details
DISTRICT
Aligarh
AGENCY
PNC-SPML-JV
SCHEME ID
20072508
SCHEME NAME
ABHAYPUR BAHLOLPUR & MOKHAMPUR PITHANPUR WSS
ESTIMATED COST
352.92
EXPENDITURE
176.78
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
27
Procured
27
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
12836.00
Meter
Length Laid
12000.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Aligarh | Gangiri | MOHKAMPUR PITHAN | 394973 | MOHKAMPUR PITHANPUR | 169 | 169 | 100% | Har Ghar Jal | Not Certified |
| 2 | Aligarh | Gangiri | MOHKAMPUR PITHAN | 394974 | PITHANPUR | 114 | 114 | 100% | Har Ghar Jal | Not Certified |
| 3 | Aligarh | Gangiri | Abhaypur Bahlolpur | 394975 | Abhaypur Bahlolpur | 330 | 1 | 0% | Work In Progress | Not Certified |