Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Aligarh | PNC-SPML-JV | 20072591 | MAHGAVAN & MADHUPUR WSS | 388.35 | 119.39 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 27 | 27 | Yes | 0 | NA | No | 16192.00 | 15148.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Aligarh | Atrauli | Madhupur | 394801 | Madhupur | 172 | 172 | 100 | Har Gar Jal | Not Certified | 
| 2 | Aligarh | Atrauli | Madhupur | 394802 | Rampur Gosai | 167 | 165 | 99 | Work In Progress | Not Certified | 
| 3 | Aligarh | Atrauli | Mahgavan | 394810 | Mahgavan | 293 | 291 | 99 | Work In Progress | Not Certified |