Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Saharanpur | NKG-PRIMUS (JV) | 20072650 | KHURD MV WSS | 253.18 | 133.07 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 27 | 27 | Yes | 0 | NA | No | 7344.00 | 7250.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Saharanpur | Punwaraka | Khurd | 383715 | Tiparpur | 4 | 1 | 25 | Work In Progress | Not Certified |
| 2 | Saharanpur | Punwaraka | Khurd | 383716 | Khurd | 535 | 523 | 98 | Work In Progress | Not Certified |
| 3 | Saharanpur | Punwaraka | Khurd | 677710 | Chaksaid Raja | 45 | 36 | 80 | Work In Progress | Not Certified |
| 4 | Saharanpur | Punwaraka | Khurd | 677711 | Sambhalki Khurd | 40 | 38 | 95 | Work In Progress | Not Certified |