Scheme Details
DISTRICT
Budaun
AGENCY
PNC-SPML-JV
SCHEME ID
20072783
SCHEME NAME
BANKOTA WATER SUPPLY SCHEME
ESTIMATED COST
452.74
EXPENDITURE
181.82
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
44
Procured
44
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
17504.00
Meter
Length Laid
17504.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Budaun | Wazirganj | Bankota | 401390 | Bankota | 954 | 954 | 100% | Har Ghar Jal | Not Certified |