Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Moradabad
AGENCY NKG-PRIMUS (JV)
SCHEME ID 20072885
SCHEME NAME SHEKHOOPUR KHAS VILLAGE WATER SUPPLY SCHEME
ESTIMATED COST 183.39
EXPENDITURE 76.72
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 1
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 16
Procured 16 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 3805.00 Meter
Length Laid 4010.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

1 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Moradabad Dingarpur Shekhoopur Khas 388446 Chiteri 210 201 96% Work In Progress Not Certified