Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Amethi | Gayatri Projects LTD | 20073015 | AHAD, GAUTAMPUR, MAJHGAWAN & ADILPUR WATER SUPPLY SCHEME | 741.22 | 435.40 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 6 | 2 | 2 | 2 | 2 | 1 | 1 | 1 | 46 | 46 | Yes | 0 | NA | No | 47816.00 | 47142.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Amethi | Jamo | Adilpur | 439532 | Adilpur | 286 | 286 | 100 | Har Gar Jal | Not Certified | 
| 2 | Amethi | Jamo | Adilpur | 439533 | Katkarpur | 63 | 56 | 89 | Work In Progress | Not Certified | 
| 3 | Amethi | Jamo | Gautampur | 439534 | Gautampur | 176 | 172 | 98 | Work In Progress | Not Certified | 
| 4 | Amethi | Jamo | Majhgawan | 439535 | Majhgawan | 84 | 84 | 100 | Har Gar Jal | Not Certified | 
| 5 | Amethi | Jamo | Majhgawan | 439536 | Machharia | 72 | 68 | 94 | Work In Progress | Not Certified | 
| 6 | Amethi | Jamo | Ahad | 439552 | Ahad | 185 | 159 | 86 | Work In Progress | Not Certified |