Scheme Details
DISTRICT
Barabanki
AGENCY
VSA
SCHEME ID
20073301
SCHEME NAME
Dundi Karaura & Piyarepur Water Supply Scheme
ESTIMATED COST
553.21
EXPENDITURE
203.45
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
4
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
1
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
11
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
30909.00
Meter
Length Laid
24800.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
4 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Barabanki | Sirauli Gauspur | Karaura | 435501 | Karaura | 248 | 248 | 100% | Har Ghar Jal | Not Certified |
| 2 | Barabanki | Sirauli Gauspur | Piarey Pur | 435504 | Piarey Pur | 250 | 247 | 99% | Work In Progress | Not Certified |
| 3 | Barabanki | Sirauli Gauspur | Piarey Pur | 435505 | Chakdhe Pur | 160 | 157 | 98% | Work In Progress | Not Certified |
| 4 | Barabanki | Sirauli Gauspur | Dundi | 435521 | Dundi | 568 | 565 | 99% | Work In Progress | Not Certified |