Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Basti | Megha | 20073338 | BARGADWA GP wss | 205.68 | 61.68 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 17 | 17 | NA | 0 | NA | No | 8009.00 | 8311.30 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Basti | Rudhauli | Bargadwa | 450691 | Pakri Awwal | 63 | 55 | 87 | Work In Progress | Not Certified |
| 2 | Basti | Rudhauli | Bargadwa | 450692 | Bargadwa | 99 | 74 | 75 | Work In Progress | Not Certified |
| 3 | Basti | Rudhauli | Bargadwa | 450693 | Phatipur | 53 | 50 | 94 | Work In Progress | Not Certified |
| 4 | Basti | Rudhauli | Bargadwa | 450694 | Kodara | 29 | 3 | 10 | Work In Progress | Not Certified |
| 5 | Basti | Rudhauli | Bargadwa | 450695 | Sihani Kurd | 54 | 48 | 89 | Work In Progress | Not Certified |