Scheme Details
DISTRICT
Hardoi
AGENCY
NCC Ltd.
SCHEME ID
20073381
SCHEME NAME
JARSENAMAU JJM
ESTIMATED COST
231.95
EXPENDITURE
151.89
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
1
Solar Plant
Required
22
Procured
22
KW
Work Status
NA
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
5428.00
Meter
Length Laid
5428.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Hardoi | Bilagram | Jarsenamau | 412681 | Jarsenamau | 268 | 268 | 100% | Har Ghar Jal | Not Certified |
| 2 | Hardoi | Bilagram | Jarsenamau | 412682 | Katri Jarsenamau | 138 | 67 | 49% | Work In Progress | Not Certified |