Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Shahjahanpur | NCC Ltd. | 20073531 | AYUN & BILAIYA WSS | 331.99 | 163.70 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 20 | 20 | Yes | 0 | NA | No | 21353.00 | 21353.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Shahjahanpur | Powayan | Ayun | 406100 | Ayun | 231 | 231 | 100 | Har Gar Jal | Certified |
| 2 | Shahjahanpur | Powayan | Billaiya | 406101 | Bilaiya | 112 | 112 | 100 | Har Gar Jal | Certified |
| 3 | Shahjahanpur | Powayan | Billaiya | 406102 | Bans Kirayun | 59 | 59 | 100 | Har Gar Jal | Certified |
| 4 | Shahjahanpur | Powayan | Billaiya | 406103 | Jamalpur | 55 | 55 | 100 | Har Gar Jal | Certified |
| 5 | Shahjahanpur | Powayan | Billaiya | 406104 | Simara | 68 | 68 | 100 | Har Gar Jal | Certified |