Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Saharanpur | NKG-PRIMUS (JV) | 20073689 | KURALI & DANIYALPUR & MADKI GP WSS | 530.16 | 102.85 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 51 | 51 | Yes | 0 | NA | No | 18572.00 | 12000.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Saharanpur | Baliakheri | Kurali | 383884 | Kurali | 319 | 313 | 98 | Work In Progress | Not Certified | 
| 2 | Saharanpur | Baliakheri | Madki | 383885 | Madki | 310 | 300 | 97 | Work In Progress | Not Certified | 
| 3 | Saharanpur | Baliakheri | Daniyalpur Urf Naujli | 383886 | Daniyalpur Urf Noojli | 574 | 574 | 100 | Har Gar Jal | Certified |