Scheme Details
DISTRICT
Pratapgarh
AGENCY
Power Mech Projects Ltd
SCHEME ID
20073826
SCHEME NAME
Jagdishpur and Purebhaiya water supply scheme
ESTIMATED COST
424.57
EXPENDITURE
289.99
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
2
Boring Done
2
Air Compressor Done
2
O.P. Unit Done
2
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
32
Procured
32
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
23368.00
Meter
Length Laid
22985.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Pratapgarh | Sadar | Pure Bhaiya | 429784 | Pure Bhaiya | 252 | 252 | 100% | Har Ghar Jal | Not Certified |
| 2 | Pratapgarh | Sadar | Jagdishpur | 429859 | Jagdishpur | 139 | 135 | 97% | Work In Progress | Not Certified |
| 3 | Pratapgarh | Sadar | Jagdishpur | 429860 | Sarai Kalyan Dev | 124 | 124 | 100% | Har Ghar Jal | Not Certified |