Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Pratapgarh
AGENCY Power Mech Projects Ltd
SCHEME ID 20073836
SCHEME NAME DEVARPATTI & SILAWATPUR WATER SUPPLY SCHEME
ESTIMATED COST 806.24
EXPENDITURE 438.06
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 2
Boring Done 2
Air Compressor Done 2
O.P. Unit Done 2
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 74
Procured 74 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 42208.00 Meter
Length Laid 42208.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Pratapgarh Vihar Silawatpur 429540 Silawatpur 277 227 82% Work In Progress Not Certified
2 Pratapgarh Vihar Dever Patti 429557 Dever Patti 1431 1429 100% Work In Progress Not Certified