Scheme Details
DISTRICT
Bareilly
AGENCY
NCC Ltd.
SCHEME ID
20073950
SCHEME NAME
Chondra Water Supply Scheme
ESTIMATED COST
206.38
EXPENDITURE
143.72
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
13
Procured
13
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
10222.00
Meter
Length Laid
10131.00
Meter
Scheme Assigned Villages
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bareilly | Faridpur | Chondra | 404354 | Chondra | 145 | 145 | 100% | Har Ghar Jal | Not Certified |
| 2 | Bareilly | Faridpur | Chondra | 404355 | Nawadia Ilaka Sahora | 61 | 61 | 100% | Har Ghar Jal | Not Certified |
| 3 | Bareilly | Faridpur | Chondra | 404356 | Bhikampur Urf Gulab Rai | 69 | 69 | 100% | Har Ghar Jal | Not Certified |