Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Bulandshahr
AGENCY Welspun Kaveri Infraprojects JV
SCHEME ID 20074037
SCHEME NAME Kapsaipur, Shadipur Banboi WSS
ESTIMATED COST 328.30
EXPENDITURE 188.40
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 30
Procured 30 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 14273.00 Meter
Length Laid 13911.00 Meter

Scheme Assigned Villages

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Bulandshahr Unchagaon Kapsai Mahmood Pur 393523 Shadipur Banboi 41 41 100% Har Ghar Jal Certified
2 Bulandshahr Unchagaon Kapsai Mahmood Pur 393524 Kapsaipur 648 648 100% Har Ghar Jal Certified