Scheme Details
DISTRICT Sambhal
AGENCY NKG-PRIMUS (JV)
SCHEME ID 20074218
SCHEME NAME MUDENA & SURPUR MV WSS
ESTIMATED COST 389.05
EXPENDITURE 150.61
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 27
Procured 27 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 15921.00 Meter
Length Laid 15900.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Sambhal Gunnaur Mudena 400936 Mudena 342 341 100% Work In Progress Not Certified
2 Sambhal Gunnaur SOORPUR 400937 SURPUR 219 219 100% Har Ghar Jal Not Certified