Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Ghazipur | HFCL- JWIL (JV) | 20074257 | JAGDISHPUR M DAHEDU W/S SCHEME (HFCL) | 320.24 | 98.58 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Ghazipur | Kasimabad | JAGDISHPUR M. DAHEDU | 473169 | Jagdishpur M. Dahedu | 139 | 128 | 92 | Work In Progress | Not Certified | Not Verified |
2 | Ghazipur | Kasimabad | JAGDISHPUR M. DAHEDU | 473170 | Nadula | 64 | 57 | 89 | Work In Progress | Not Certified | Not Verified |
3 | Ghazipur | Kasimabad | JAGDISHPUR M. DAHEDU | 677930 | Baragaon M. Dariyapur | 130 | 117 | 90 | Work In Progress | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
3 | 2 | 2 | 2 | 2 | 1 | 0 | 0 | 13 | 13 | Yes | 0 | NA | No | 10691.00 | 8163.00 |