Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Ghazipur
AGENCY HFCL- JWIL (JV)
SCHEME ID 20074299
SCHEME NAME DEVAPAR W/S SCHEME (HFCL)
ESTIMATED COST 227.11
EXPENDITURE 120.05
AUTOMATION STATUS
Disconnected View Live Screen
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 16
Procured 16 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 9742.00 Meter
Length Laid 10108.70 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Ghazipur Sadat Devapar 471912 Devapar 230 217 94% Work In Progress Not Certified
2 Ghazipur Sadat Devapar 471913 Ratanagar Pur 50 46 92% Work In Progress Not Certified