Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Chandauli | VSA | 20074356 | Alampur WS | 633.50 | 250.70 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 28 | 28 | Yes | 0 | NA | No | 13647.00 | 13647.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Chandauli | Sakaldiha | Alampur | 474523 | Alampur | 437 | 437 | 100 | Har Gar Jal | Not Certified |
| 2 | Chandauli | Sakaldiha | Alampur | 474524 | Mustafapur | 106 | 104 | 98 | Work In Progress | Not Certified |
| 3 | Chandauli | Sakaldiha | Alampur | 474525 | Khan Jahan Chak | 79 | 77 | 97 | Work In Progress | Not Certified |
| 4 | Chandauli | Sakaldiha | Alampur | 474526 | Muhammadpur | 77 | 77 | 100 | Har Gar Jal | Not Certified |